When a main contractor on a Saudi infrastructure project enters restructuring proceedings, a subcontractor holding unpaid certified progress payments does not automatically lose those claims – but the window to protect them is narrow and procedurally unforgiving. The correct response is to map each certified payment separately, assess suspension and direct-payment rights under the applicable subcontract and Saudi law, and lodge a formally documented creditor claim before any statutory deadline closes. Acting without that map – whether by pulling equipment off site immediately or by filing a single aggregated ledger balance – can compromise both recovery and the subcontractor's position on the continuing works.
Recognising the Situation
This model situation centres on a UAE-registered engineering services contractor that has been working as a subcontractor on a large infrastructure project in Saudi Arabia. Works have been executed across multiple monthly periods, interim payment certificates have been issued by the employer's engineer, and a retention percentage has been withheld in the customary manner. The main contractor has now announced a formal restructuring and offered subcontractors a one-year deferral of all outstanding sums while simultaneously demanding that work continue on the next phase.
The commercial exposure here is substantial. The subcontractor carries approximately USD 2.4 million in progress payments that have been certified but not settled, plus an unliquidated retention amount that becomes due only upon completion milestones. At the same time, the subcontractor has equipment, personnel and ongoing contractual obligations on the site. This combination – creditor status in a restructuring and ongoing performance obligations – is one of the most difficult positions in construction law.
Many companies in this position assume the restructuring is a force majeure that dissolves their obligations, or conversely that they must keep working indefinitely because stopping will trigger liquidated damages. Neither assumption is correct without reading the contract carefully against the applicable law.
What Is Really at Stake
The risks facing the subcontractor operate on three levels simultaneously:
- Financial exposure: USD 2.4 m in unpaid certified amounts, plus the potential for further sums to become unpaid if work continues without security. If the restructuring becomes a full insolvency, unsecured creditors in Saudi proceedings typically recover only a fraction of proven claims, and only after a process that may take several years.
- Operational exposure: Equipment and personnel on site represent a continuing cost drain. If the subcontractor suspends works without contractual justification, it may face a counterclaim for delay damages under the subcontract, potentially offsetting or exceeding the debt owed to it.
- Evidentiary exposure: The subcontractor's project manager has already threatened to remove equipment without a formal suspension notice, and the accounts team has submitted a consolidated ledger rather than certified-payment-by-certified-payment documentation. Both actions weaken the creditor position and must be corrected urgently.
There is also a jurisdiction-specific dimension. The subcontractor is UAE-registered but the project is in Saudi Arabia. The subcontract may designate Saudi law as governing law and Saudi courts or arbitration as the dispute resolution forum, or it may contain a different choice. The main contractor's restructuring will almost certainly be governed by Saudi insolvency law. These are distinct legal frameworks, and the remedies available depend on which applies to which part of the claim.
The Legal Framework: Saudi Construction and Insolvency Law
Governing Law of the Subcontract
Saudi Arabia does not have a single consolidated construction statute. Construction contracts on Saudi projects are typically governed by the Civil Transactions Law (issued by Royal Decree No. M/191 of 1444H, in force since 16 June 2023), which introduced codified rules on contracts of work (muqawala), including provisions on payment obligations, right of suspension and termination. Prior to that law's entry into force, courts applied Sharia-based principles and analogical reasoning from the Saudi Civil Code tradition. For works begun before the Civil Transactions Law's commencement, transitional provisions and the date of contract formation will affect which rules apply.
On government infrastructure projects in Saudi Arabia, the standard contract forms are frequently based on FIDIC (the Red or Yellow Book) adapted to Saudi requirements, or on the Government Tenders and Procurement Law framework. Where FIDIC Sub-Clause 16.1 or an equivalent provision is incorporated, it gives the subcontractor a right to suspend work after a defined notice period if payment is overdue, subject to conditions. Whether that right flows down to the subcontractor depends on how the subcontract is drafted – back-to-back or standalone.
Pay-When-Paid Clauses
Saudi law does not have a statutory prohibition on pay-when-paid clauses equivalent to those found in some common law jurisdictions. Where such a clause is present in the subcontract, the subcontractor's right to payment may be conditional on the main contractor receiving funds from the employer. However, if the main contractor is in restructuring or insolvency, courts and arbitral tribunals have sometimes held that a pay-when-paid clause cannot operate indefinitely as a defeater of the subcontractor's claim – the question is fact-specific and depends on the clause's exact wording and the governing law. This analysis requires review of the actual subcontract.
Saudi Insolvency and Restructuring Law
Saudi Arabia's insolvency regime is governed by the Bankruptcy Law issued by Royal Decree No. M/50 of 1439H (2018), implemented through its Implementing Regulations. The law established a modern restructuring procedure (the protective settlement or financial restructuring route) modelled partly on internationally recognised frameworks, administered through the courts with supervision by licensed insolvency practitioners. When a main contractor files for or is admitted to a protective settlement procedure, an automatic stay on creditor enforcement actions is typically imposed, and creditors must file their claims within the deadlines notified by the court-appointed supervisor.
Critically, the Bankruptcy Law distinguishes between:
- Secured creditors – those with registered pledges, mortgages or retention-of-title rights over assets;
- Preferential creditors – including certain employee wage claims;
- Unsecured creditors – the class in which a subcontractor with an unpaid certified payment will ordinarily fall, absent special security arrangements.
Filing a timely, fully documented creditor claim in the restructuring is not optional if the subcontractor wishes to participate in any distribution or vote on a restructuring plan. Missing the filing deadline can result in the claim being treated as late, subordinated or excluded entirely, depending on the stage of the proceedings.
Direct Payment Rights Against the Employer
Saudi law and certain Saudi government procurement instruments do contain mechanisms by which a subcontractor may in some circumstances seek payment directly from the ultimate employer (the government entity commissioning the project). However, this is not an automatic right. It generally requires either: (a) an express contractual provision in the main contract permitting or requiring direct payment to named subcontractors, or (b) a specific government policy applicable to the particular project, or (c) court authorisation within insolvency proceedings. Proceeding against the government employer without establishing one of these foundations is a significant procedural error that can result in the claim being dismissed and generating adversarial attention from the employer. The main contract – to which the subcontractor is not typically a party – must be reviewed (or disclosed through litigation/arbitration) before any direct payment claim is pursued.
Realistic Routes and Their Trade-offs
Route A: Segregate, Certify and File a Structured Creditor Claim
The first and most time-sensitive action is to reconstruct the payment exposure as a series of discrete, certified claims rather than a single aggregate balance. Each interim payment certificate should be identified by date, amount, the works it covers and its current status (unpaid, partially paid, disputed). Variation orders should be listed separately, with supporting documentation for each instruction and the valuation basis. The retention sum should be identified with reference to the contractual milestone that triggers its release.
This segregated exposure schedule serves two purposes: it is the evidential foundation for a creditor claim in the restructuring proceedings, and it separates the uncontested certified sums (strongest position) from disputed variations (which will require more negotiation or adjudication). Filing a single consolidated figure without supporting documentation – as the subcontractor's accountant has done – is one of the most common errors in this scenario and can result in the claim being reduced, challenged or rejected by the insolvency supervisor.
Advantages: Preserves the creditor position; complies with Bankruptcy Law filing requirements; creates a clean evidential record for any subsequent arbitration or litigation.
Disadvantages: Time-consuming to reconstruct if records have not been maintained in segregated form; does not by itself generate cash in the short term.
Route B: Negotiate Security for Continuing Works
If the subcontractor is willing to continue working on the new phase – commercially, there may be strong reasons to do so – it should not do so without obtaining written security for the continuing obligations. Options include:
- An escrow arrangement under which the employer (or a neutral bank) holds progress payments for the new phase and releases them directly to the subcontractor upon certification, bypassing the main contractor's distressed balance sheet;
- A parent company guarantee or bank guarantee from a solvent member of the main contractor's group;
- A formal direct payment letter signed by the employer, the main contractor and the subcontractor, acknowledging the arrangement and the amounts outstanding.
These arrangements require the cooperation of the main contractor and, in some cases, the employer. The main contractor's insolvency process may actually create an incentive for the employer to agree to escrow or direct payment arrangements to keep the project moving – this is a commercial lever the subcontractor can use. Any such arrangement must be documented in a signed, written instrument before work on the new phase begins.
Advantages: Protects future cash flows; maintains the commercial relationship and site presence; avoids the costs and delays of litigation.
Disadvantages: Depends on counterparty cooperation; does not resolve the existing USD 2.4 m debt; requires careful drafting to avoid inadvertently waiving existing claims.
Route C: Formal Dispute Resolution – Arbitration or Court Proceedings
If negotiation fails and the restructuring proceedings do not produce an acceptable outcome, the subcontractor has the option of pursuing its claim through the contractually agreed dispute resolution mechanism. For Saudi construction projects, this is frequently arbitration (the Saudi Center for Commercial Arbitration, SCCA, is the main institutional body; ad hoc arbitration under UNCITRAL rules is also used) or litigation before the Saudi Commercial Courts. Where the subcontract has a UAE arbitration clause, the dispute would proceed under UAE arbitration law (Federal Decree-Law No. 6 of 2018, the UAE Arbitration Law) before an institution such as the DIAC or ADGM arbitration centre.
Arbitration in the construction context has the advantage of technical expertise and confidentiality. However, an arbitral award against a main contractor in restructuring will typically be subject to the automatic stay imposed by the bankruptcy proceedings and may need to be proved as a claim in those proceedings in any event. Obtaining the award may still be valuable – it crystallises the debt, establishes its quantum and may convert a disputed claim into an undisputed one for insolvency purposes.
Advantages: Creates a binding legal determination; can be enforced if the main contractor emerges from restructuring with assets.
Disadvantages: Time and cost of arbitration proceedings; the stay in bankruptcy proceedings may suspend enforcement; legal costs are an additional cash burden on the subcontractor.
| Route | Speed | Cash Impact | Requires Counterparty Cooperation | Risk to Site Position |
|---|---|---|---|---|
| A – Structured Creditor Claim | Medium (tied to insolvency timetable) | Deferred; depends on restructuring outcome | No (court process) | Low if suspension handled correctly |
| B – Escrow / Security for New Works | Fast if agreed | Positive for future phases | Yes (main contractor and employer) | Low; maintains relationship |
| C – Arbitration / Court | Slow (months to years) | Negative short-term; potential recovery | No | Medium to high depending on suspension |
Suspension of Works: Rights, Risks and the Correct Procedure
The right to suspend works for non-payment is one of the most powerful tools available to a subcontractor – and one of the most dangerous if exercised incorrectly. Under FIDIC Sub-Clause 16.1 (Red Book, 2017 edition), the contractor must give not less than 21 days' notice before suspending or reducing the rate of works, and the right arises only where the contractor has not received the amount due under an interim payment certificate within the time stated in the contract. The equivalent provision in the Yellow Book (design-build) is substantively similar.
Where the subcontract is back-to-back with a FIDIC main contract, the suspension right mirrors this structure. Where the subcontract uses a bespoke form, the specific wording controls. The critical rules are:
- Notice must be given in writing, in the form required by the subcontract, and within any notice deadline;
- The notice must identify the specific amounts overdue and the certificates they relate to;
- Work must not be suspended before the notice period expires;
- If the main contractor corrects the default within the notice period, the right to suspend lapses for that cycle.
The subcontractor's project manager's threat to remove equipment immediately, without a formal written notice and without allowing the notice period to run, would constitute a wrongful suspension if acted upon. This would potentially give the main contractor (and through it, the employer) a counterclaim for delay damages that could significantly exceed the sums owed. Any such action must be stopped and replaced with a proper written notice process.
Typical Mistakes and What Cannot Be Promised
Based on the dynamics of this model situation, the following errors are particularly common and must be avoided:
- Filing a single aggregate claim without supporting documentation for each certified period. The insolvency supervisor has the power to reject or reduce undocumented claims.
- Assuming a direct payment right against the government employer without establishing the contractual or statutory basis. Proceeding without that basis is a significant procedural misstep.
- Continuing to work on new phases without written security, on the basis of verbal assurances from the restructuring main contractor. Those assurances have no legal weight.
- Treating a pay-when-paid clause as an absolute bar without having it analysed. The clause's enforceability in an insolvency context is a legal question, not a commercial given.
- Missing the creditor claim deadline in the insolvency proceedings. This is probably the single most damaging error, and the deadline is typically short from the date of the court's admission of the restructuring application.
It is equally important to understand what cannot be promised or guaranteed. No adviser can guarantee that the restructuring will produce a satisfactory outcome for creditors, that an arbitral award will be enforced before the main contractor's assets are distributed, or that the employer will agree to an escrow or direct payment arrangement. The subcontractor's recovery depends on the main contractor's asset position, the quality of the documentation, the procedural correctness of the creditor filing and, ultimately, the decisions of the Saudi courts and insolvency supervisor.
If you are a subcontractor holding uncollected certified payments and your main contractor has announced a restructuring, the time to review your creditor position and contractual remedies is now – not after the creditor filing deadline has passed. Contact us at info@ferrazwhitmore.com or visit our contacts page to discuss how we can help map your exposure and connect you with the right local specialists in Saudi Arabia.
Documents and Evidence: What You Need Before Any Action
Assembling and organising documentary evidence is a precondition to every route described above. The following documents should be located and reviewed as an immediate priority:
- The subcontract – including all annexes, schedules, supplementary conditions and any amendments executed during the project;
- All interim payment certificates issued by the engineer, with dates and amounts;
- Payment records – what has been received, when and against which certificate;
- Variation orders – instructions, valuations and any approvals or rejections;
- Retention statements – the contractual retention rate, amounts withheld per period and the conditions for release;
- The official restructuring notice from the main contractor, any court order admitting the proceedings and the name and contact details of the insolvency supervisor;
- An equipment and personnel inventory as at the date of the restructuring announcement – this establishes the value of assets at risk and supports any claim for loss if suspension becomes necessary;
- All correspondence between the subcontractor and the main contractor regarding payment, delays, instructions and the restructuring – including emails, WhatsApp messages and meeting minutes.
From this material, an exposure schedule should be prepared – a document that sets out, line by line, each certified period, the amount certified, the amount paid, the net outstanding sum, any variations and their status, and the retention balance. This schedule is the foundation of the creditor claim and of any arbitration or litigation.
Timeline and Cost Drivers
The urgency of this situation is critical. The Saudi Bankruptcy Law requires creditors to file their claims within the period specified in the court's admission order, which is published and notified to known creditors. If that deadline is missed, the claim may be treated as a late claim with reduced priority. It is therefore essential to identify whether and when such an order has been issued and what deadline it sets.
Beyond the filing deadline, the following timeline factors are relevant:
- The notice period before suspension can lawfully take effect (dependent on the subcontract, but typically expressed in days from a written notice);
- The period within which the main contractor can cure a payment default and prevent suspension;
- The time limits for commencing arbitration under the subcontract's dispute resolution clause (usually measured from the date of the dispute notice or the engineer's decision);
- The duration of the restructuring proceedings themselves – Saudi protective settlement proceedings are time-limited by statute, but extensions are possible.
The principal cost drivers in this scenario are: the complexity of reconstructing payment records if documentation is disorganised; the need for licensed Saudi construction and insolvency counsel to handle local proceedings; translation costs if key documents are in English and need to be presented in Arabic for Saudi proceedings; and the duration of any arbitration. Early investment in a clear exposure schedule and a properly drafted creditor claim is likely to be significantly less expensive than attempting to correct procedural errors after the fact.
Decision Checklist
- Obtain the official restructuring notice and identify the court, the insolvency supervisor and the creditor filing deadline.
- Reconstruct the exposure schedule – every certified payment, variation and retention item, separately documented.
- Review the subcontract for pay-when-paid clauses, suspension rights, notice requirements, dispute resolution provisions and any direct payment mechanism.
- Issue a formal written payment notice (if not already done) for each overdue certified sum, in the form required by the subcontract.
- Do not suspend works without following the contractual notice procedure precisely.
- Do not file a consolidated claim in the insolvency proceedings without segregated, certified documentation.
- Do not pursue a direct payment claim against the employer without first establishing the contractual or statutory basis.
- Engage licensed Saudi construction and insolvency counsel before taking any formal legal step in the Kingdom.
- Negotiate security for new-phase works (escrow, guarantee, direct payment letter) before mobilising further resources.
- Preserve all correspondence and site records from the date of the restructuring announcement.
Ferraz & Whitmore advises on the cross-border structuring of creditor claims and the coordination of multi-jurisdiction construction disputes. Where local Saudi representation is required, we work alongside licensed Saudi counsel. To discuss your specific position, write to us at info@ferrazwhitmore.com or visit our contacts page.
The UAE Dimension: When Your Home Jurisdiction Matters
The subcontractor is incorporated in the UAE. This creates both practical and legal dimensions that sit alongside the Saudi proceedings.
First, if the subcontract was executed in the UAE or contains a UAE governing law clause (not uncommon in UAE-Saudi bilateral construction projects), UAE law may govern certain aspects of the contractual relationship. The UAE Civil Transactions Law (Federal Law No. 5 of 1985, as amended) contains provisions on contracts of work (muqawala) including rules on payment timing and suspension. The UAE Civil Procedure Law and Federal Decree-Law No. 6 of 2018 (the UAE Arbitration Law) would govern UAE-seated arbitration proceedings.
Second, if the subcontractor holds assets or bank accounts in the UAE, it should consider whether any Saudi court order or arbitral award could be enforced against the main contractor's UAE assets – the UAE and Saudi Arabia are both members of the Riyadh Arab Agreement for Judicial Cooperation (the Riyadh Convention), which provides a treaty framework for the mutual recognition and enforcement of judgments between Arab League member states. The practical operation of this convention in construction debt recovery contexts requires case-specific advice.
Third, the subcontractor should review whether its own contractual position with its UAE-based suppliers, equipment lessors or financiers is affected by the main contractor's restructuring – for example, if any equipment on the Saudi site is subject to a lease or charge registered under UAE law, the equipment inventory and removal question has an additional legal dimension.
These cross-border elements – UAE entity, Saudi project, potentially hybrid contract – are precisely the kind of situation where early mapping of applicable law, jurisdiction and enforcement routes prevents costly procedural errors later.
If this situation resembles your own and you would like an initial mapping of your legal position and filing deadlines, please contact us at info@ferrazwhitmore.com or through our contacts page.
Sources
- Saudi Civil Transactions Law, Royal Decree No. M/191 of 1444H (2023) – governing contract of work (muqawala), payment obligations and suspension rights under Saudi law, retrieved 2026
- Saudi Bankruptcy Law, Royal Decree No. M/50 of 1439H (2018) – creditor claim filing requirements, restructuring procedure, automatic stay and creditor classes, retrieved 2026
- Implementing Regulations of the Saudi Bankruptcy Law – procedural rules for protective settlement and creditor claim deadlines, retrieved 2026
- Saudi Center for Commercial Arbitration (SCCA) – institutional arbitration rules applicable to Saudi construction disputes, retrieved 2026
- Saudi Government Tenders and Procurement Law, Royal Decree No. M/128 of 1440H (2019) – framework governing government construction procurement and subcontracting in Saudi Arabia, retrieved 2026
- FIDIC Conditions of Contract for Construction (Red Book, 2nd Edition, 2017) – Sub-Clause 16.1 on suspension rights and notice requirements, retrieved 2026
- UAE Federal Decree-Law No. 6 of 2018 on Arbitration – UAE arbitration law applicable where subcontract seats arbitration in the UAE, retrieved 2026
- UAE Civil Transactions Law, Federal Law No. 5 of 1985 (as amended) – UAE rules on contracts of work and payment obligations, retrieved 2026
- Riyadh Arab Agreement for Judicial Cooperation (1983) – treaty framework for mutual recognition and enforcement of judgments between Arab League states including UAE and Saudi Arabia, retrieved 2026
- UNCITRAL Legislative Guide on Insolvency Law – international reference framework for creditor rights and cross-border insolvency coordination, retrieved 2026
Disclaimer: This article describes a model client situation for informational purposes only and does not constitute legal advice, nor does it reflect an actual Ferraz & Whitmore engagement or outcome. Legal routes are described as options, not guarantees. Applicable law, procedure and the right to provide a given service in each jurisdiction must be confirmed for any specific matter. Ferraz & Whitmore is an independent legal advisory firm based in Lisbon, Portugal; where local representation is required, it works with licensed local counsel. For advice on your situation, contact info@ferrazwhitmore.com.