Your Solar JV Partner Missed the Permit Milestones – Should You Extend the Agreement or Exit and Recover Your Investment?

When a local development partner in a cross-border solar joint venture fails to secure land rights or grid-connection permits by the contractually agreed milestone dates, the foreign investor is left holding a capital contribution, a deteriorating financing timeline, and an increasingly uncertain path to returns. The central legal question is whether the partner's obligation was an absolute milestone commitment or merely a "best endeavours" undertaking – because that distinction determines whether a breach has occurred, what damages flow from it, and whether contractual exit rights have been triggered. Resolving that question requires a careful reading of the joint venture agreement against the applicable law, followed by a structured decision between renegotiation, a funded extension with strengthened protections, or a disciplined exit designed to preserve as much of the invested capital as possible.

Recognising the Problem

This model situation involves a Spanish investment company that has committed capital into a Romanian solar energy project through a joint venture structure valued at approximately €9 million. The local Romanian development partner undertook, under the joint venture agreement (JVA), to complete two critical preparatory stages – securing the necessary land rights and obtaining a grid-connection approval – by fixed contractual dates. Eight months into the project, neither obligation has been fulfilled. The project financing facility requires extension, the meter is running on costs, and the investor must decide whether to continue or to exit.

This scenario is recognisable to any foreign equity investor in European renewable energy projects: the local partner controls the regulatory relationships and the permitting process; the foreign investor controls the capital. When the two are misaligned, the foreign investor can find themselves exposed to a situation where continuing means committing more funds to an uncertain process, and stopping means crystallising a loss on sunk capital.

The situation is complicated further by the fact that permitting in the renewable energy sector – particularly in Romania, where the grid operator is Transelectrica S.A. and grid-connection approvals are governed by sectoral regulation under the authority of the Autoritatea Națională de Reglementare în domeniul Energiei (ANRE) – involves a sequence of administrative steps that are not always within the developer's direct control. That regulatory complexity does not, however, automatically excuse a contractual obligation, particularly where the milestone was drafted as an absolute deadline rather than a reasonable-efforts standard.

What Is Really at Stake

The investor's principal concerns fall into three categories:

  • Capital preservation: The equity contribution already paid into the JV structure must be accounted for. If the project does not proceed, the investor needs to understand whether that capital can be returned through a contractual waterfall, through liquidation of project assets (land, equipment, any partially obtained permits), or through a damages claim.
  • Project viability: If the permitting obstacles are temporary and curable, extending the arrangement may still yield a functioning project. The investor needs an honest assessment of whether the delays are systemic, whether the partner has the capacity and relationships to complete the process, and what a realistic revised timeline looks like.
  • Contractual leverage: Every day that passes without a formal legal response risks eroding the investor's position. If the investor has already issued a notice of delay and informally proposed an extension in exchange for additional equity, that is a double-edged action: it demonstrates good faith, but it may also have reset the clock or inadvertently waived a strict breach right if the new proposal was not carefully conditioned.

Beyond these immediate concerns, there is a secondary layer of risk involving the ownership of the permits and project assets. In many jurisdictions, permits attach to the entity that applied for them, not necessarily to the JV as a whole. Understanding who legally holds – or will hold – the grid-connection application, any preliminary approvals, and the land-use rights is essential before any restructuring or exit is planned.

The Legal Fork: Key Issues Under the JVA

Absolute Obligation vs. Best Endeavours

The single most important contractual question is how the milestone obligations were drafted. Under both Romanian civil law (governed by the Codul Civil, Law No. 287/2009, as republished) and Spanish civil law (governed by the Código Civil), a distinction exists between an obligation to achieve a specific result (obligație de rezultat / obligación de resultado) and an obligation to make reasonable or best efforts toward a goal (obligație de diligență / obligación de medios). This distinction is not merely academic: it determines the threshold for breach and the standard of proof required.

If the milestone was drafted as an absolute obligation – "Partner shall obtain grid-connection approval by [date]" – then failure by that date constitutes a breach regardless of the reasons. If it was drafted as a best-endeavours or reasonable-efforts clause, the investor must demonstrate not only that the deadline was missed but also that the partner failed to take all steps that a competent developer in the same position would have taken. Courts in both Romania and Spain have addressed this distinction, and the analysis will be highly fact-specific and document-intensive.

The Long-Stop Date

Many JVAs in the renewable energy sector include a long-stop date: a final backstop deadline after which either party may terminate the agreement without liability (or with specific consequences such as a return of contributed capital). The long-stop date is a critical tool for investors because it converts an open-ended permitting process into a bounded risk. If the JVA contains such a provision, the investor must determine:

  • whether the long-stop date has already passed or is approaching;
  • whether any notice requirement must be satisfied before the long-stop termination right can be exercised;
  • whether the investor's earlier notice of delay and proposal for extension has had any effect on the long-stop mechanism; and
  • what consequences attach to termination at the long-stop – in particular, whether capital is returned and in what order.

Put Options and Exit Rights

Some JVAs grant one or both parties a put option: the right to require the other party to purchase the exiting party's interest at a pre-agreed price or formula. If such a right exists and has been triggered by the partner's failure, exercising it may be the most efficient route to capital recovery. The analysis must confirm whether the trigger conditions have been met, whether the valuation mechanism is workable in the current state of the project (a project without permits may be valued very differently from the original equity contribution), and whether the counterparty has the financial capacity to honour the obligation.

Title to Permits and Project Assets

Grid-connection approvals and land-use permits in Romania are issued to the applicant entity by ANRE and by the relevant land registry (Agenția Națională de Cadastru și Publicitate Imobiliară – ANCPI). If the permitting applications were submitted in the name of the local partner entity rather than the JV vehicle, the investor may not have direct rights over those approvals even if the project fails. This is a structural issue that needs to be identified and addressed in any restructuring or exit negotiation.

Applicable Law and Dispute Resolution

JVAs involving Spanish and Romanian parties frequently specify a neutral governing law – sometimes English law, sometimes the law of one of the contracting parties' jurisdictions, sometimes another EU member state's law. The applicable law will govern the interpretation of milestone obligations, the consequences of breach, and the available remedies. The dispute resolution clause – whether ICC or LCIA arbitration, ad hoc arbitration under UNCITRAL Rules, or litigation in a specified national court – will determine the procedural path for any formal claim. Both must be identified before any formal step is taken.

Realistic Routes and Trade-offs

Route A: Renegotiate Milestones With Strengthened Protections

If the project remains commercially viable and the partner has credible reasons for the delay – for example, documented administrative backlog at ANRE or a pending change in grid regulation – the investor may prefer to extend the arrangement rather than exit. However, any extension must be structured so that it does not inadvertently waive the existing breach or weaken the investor's position for a future exit.

A properly structured extension would include:

  • new milestone dates that are realistic and independently verified, with intermediate reporting obligations;
  • a step-in right allowing the investor (or a nominated third party) to take over permitting activities if the partner again fails to meet an intermediate milestone;
  • a strengthened long-stop date with automatic termination and capital return consequences;
  • a requirement that all permitting documentation, correspondence with ANRE and grid operators, and land registry filings be held in a shared data room accessible to the investor;
  • express confirmation that the extension does not constitute a waiver of rights arising from the original breach; and
  • a valuation mechanism for the project assets agreed in advance, so that any future exit or put exercise is not contested.

Trade-offs: This route preserves the possibility of a functioning project and avoids the cost and uncertainty of litigation or arbitration. Its downside is that it commits more time and potentially more capital to a situation where the partner has already demonstrated an inability to deliver on schedule. It is also the route most likely to be proposed by the partner, which means the investor must be disciplined about the terms on which extension is granted.

Route B: Exercise the Contractual Exit Right

If the JVA contains a put option, a long-stop termination right, or a specific exit mechanism tied to milestone failure, exercising it in accordance with its terms may be the cleanest route to capital recovery. The key steps are:

  • confirming that the trigger conditions have been met and that any required notice has been or is being served correctly;
  • identifying the agreed purchase price or valuation formula and assessing whether it is realistic in the current state of the project;
  • understanding the waterfall for return of capital, including whether interest accrues on unreturned amounts;
  • preparing for the possibility that the partner will dispute the valuation or the trigger conditions, requiring mediation, arbitration, or court proceedings to resolve; and
  • ensuring that the exit mechanics include provisions for the transfer or assignment of any partially obtained permits or project rights.

Trade-offs: A clean contractual exit is the fastest route to certainty, but only if the partner complies voluntarily. If the partner disputes the exit or cannot pay, the investor is back in a dispute process. The valuation of a project that lacks permits may also be significantly below the invested capital, meaning that exercising a contractual exit right does not necessarily recover the full contribution.

Route C: Formal Claim for Breach of Contract

If the milestone obligation was absolute, the breach is demonstrable, and the investor has suffered quantifiable losses (including financing costs, development costs, and consequential losses), a formal damages claim through arbitration or litigation may be available. The investor would need to demonstrate:

  • the existence and terms of the obligation;
  • the fact of non-performance by the relevant date;
  • that the non-performance was not excused by a force majeure provision or by the investor's own conduct;
  • the quantum of loss, with supporting documentation (invoices, financing agreements, independent valuations); and
  • a causal link between the breach and the loss.

Trade-offs: A formal claim provides the most direct path to full compensation if the case is strong and the counterparty is solvent. However, arbitration and cross-border litigation are costly, time-consuming, and uncertain in outcome. For a €9 million project, the cost-benefit analysis of pursuing a formal claim depends heavily on the strength of the documentary evidence, the quality of the breach provisions in the JVA, and the financial position of the local partner.

If you are facing a permit milestone failure in a cross-border JV and are unsure which route best protects your position, we welcome an initial review. Please contact us at info@ferrazwhitmore.com or visit our contacts page.

Typical Mistakes and What Cannot Be Promised

Mistakes That Erode the Investor's Position

  • Extending without conditions: Granting an informal or unstructured extension – even by simply not enforcing a deadline – can be construed as a waiver of the original breach. Any agreement to allow more time must be documented, conditional, and expressly stated not to constitute a waiver of accrued rights.
  • Failing to follow notice requirements: JVAs frequently require formal written notice as a precondition to exercising termination rights, put options, or bringing a damages claim. If the contractual notice mechanism has not been followed correctly – wrong recipient, wrong form, wrong timeframe – the investor may find that its rights have not been validly triggered. The earlier notice of delay sent by the investor in this scenario must be reviewed for compliance with the contractual notice clause.
  • Editing or curating the evidence chain: When preparing for a potential dispute, there is a natural temptation to present only the most favourable documents. This is counterproductive: in any arbitration or litigation, the opposing party will have access to discovery or document production, and gaps in the evidence chain will be noted. The investor should preserve all original correspondence, permitting timelines, grid-connection documents, development invoices, and board minutes in unaltered form.
  • Overlooking who holds the permits: As noted above, if the grid-connection application and land rights are held in the name of the local partner entity, they may not automatically transfer to the investor or the JV vehicle on exit. This needs to be addressed contractually in any restructuring or exit agreement.
  • Ignoring the limitation period: Claims for breach of contract are subject to limitation periods under the applicable law. Under the Romanian Civil Code (Law No. 287/2009, Article 2517), the general limitation period for contractual claims is three years. Under the Spanish Civil Code (Articles 1964 and following), the limitation period for personal actions is five years. If arbitration is specified, the applicable institutional rules or the law governing the arbitration agreement will determine any procedural time constraints. These periods run from the date on which the right to claim arises – which may be the date of the missed milestone.

What Cannot Be Promised

No legal adviser can promise a specific outcome in a situation of this kind. Whether a court or tribunal will find that the milestone obligation was absolute or merely a best-efforts standard, whether a damages claim will succeed, and what a project asset might realise on exit, all depend on facts, documents, and legal arguments that have not yet been fully assembled. What a disciplined legal review can do is map the available routes, identify the strongest and weakest points of each, and help the investor make a rational, informed decision about which path to pursue.

Documents and Evidence: What to Gather First

Before any formal step is taken, the investor should assemble the following documents in their original, unedited form:

  • The joint venture agreement (JVA) and any shareholders' agreement (SHA), including all schedules, annexes, and any subsequent amendments;
  • The permitting timeline agreed between the parties, including any internal project plan or Gantt chart shared between the partners;
  • All correspondence with ANRE, the grid operator (Transelectrica or the relevant distribution network operator), and the land registry (ANCPI), including application submissions, acknowledgements, requests for further information, and any rejection or deferral notices;
  • Development invoices and payment records evidencing the sums contributed by the investor to date;
  • Board minutes or management committee resolutions of the JV entity;
  • The notice of delay sent by the investor, together with proof of delivery;
  • Any written or email response from the local partner; and
  • The financing facility documentation, including any extension requests or lender correspondence related to the permitting delay.

Once this package is assembled, the first analytical step is to prepare a factual chronology mapping each contractual obligation against the documented evidence of what actually happened. This chronology forms the backbone of any subsequent legal analysis, negotiation, or formal claim.

Timeline and Cost Drivers

The timeline for resolving a situation of this kind depends on the route taken:

Route Indicative Timeline Key Cost Drivers
Renegotiation of milestones 4–12 weeks (negotiation and documentation) Complexity of revised terms; valuation of step-in rights; local legal costs in Romania and Spain
Contractual exit (put option / long-stop) 8–16 weeks if uncontested; 12–24 months if disputed Valuation disputes; partner's financial capacity; transfer of permits and assets
Formal arbitration or litigation 18–36 months or longer depending on institution and seat Arbitrator/court fees; expert witnesses (permitting, valuation); document production; enforcement proceedings

The most significant cost driver across all routes is the quality and completeness of the contractual documentation. A well-drafted JVA with clear milestone definitions, a workable long-stop clause, and a specified dispute resolution mechanism substantially reduces the cost and uncertainty of any resolution path. Where the original documentation is ambiguous or incomplete, the investor should expect higher costs and longer timelines regardless of the route chosen.

A second major cost driver is the jurisdictional complexity. Any formal claim involving a Spanish investor and a Romanian entity operating assets in Romania will engage questions of applicable law, enforcement of awards or judgments across EU member states (governed by Regulation (EU) No 1215/2012 – the Brussels I Recast Regulation – for court judgments, and the New York Convention on the Recognition and Enforcement of Foreign Arbitral Awards 1958 for arbitral awards), and the need for locally licensed lawyers in both jurisdictions to advise on national regulatory and procedural requirements.

Decision Checklist

Before committing to a course of action, an investor in this situation should be able to answer the following questions:

  • Is the milestone obligation in the JVA drafted as an absolute obligation or a best-efforts standard?
  • Has a formal notice of breach been served in compliance with the contractual notice requirements?
  • Does the JVA contain a long-stop date, and if so, has it been triggered or is it approaching?
  • Does the JVA contain a put option or specific exit mechanism, and have its trigger conditions been met?
  • Who holds legal title to the grid-connection application, the land rights, and any equipment already acquired?
  • What is the current status of the permitting process at ANRE – is there a pending application, a deferral, or a rejection?
  • What is the financial position of the local partner, and would it be able to honour a put option or damages award?
  • Has the investor's earlier proposal for an extension been conditioned and documented in a way that preserves its existing contractual rights?
  • What is the applicable law and the dispute resolution clause, and have limitation period implications been considered?
  • Has the full documentary evidence chain been preserved and assembled in unedited form?

If the answers to several of these questions are unclear, the most useful immediate step is a structured legal review of the JVA and the available documentation before any further negotiation takes place. At Ferraz & Whitmore, we provide preliminary documentary diagnostics for cross-border JV disputes of this kind, working in coordination with licensed local lawyers in Spain and Romania for questions of national law. To request an initial review, please write to us at info@ferrazwhitmore.com.

Romania-Specific Regulatory Context

Understanding the Romanian permitting process is relevant to assessing whether the local partner's delay can be attributed to genuine regulatory obstruction or to a failure of diligence. Grid-connection in Romania for new generation capacity is governed by regulations issued by ANRE. The process involves a formal grid-connection study (studiu de racordare), issuance of a technical solution (soluție tehnică), and ultimately a grid-connection contract with the relevant operator. ANRE publishes its secondary legislation and regulatory decisions in the Monitorul Oficial al României (Official Gazette of Romania), which is the authoritative source for applicable regulatory requirements.

Land rights for solar projects may involve agricultural land, which in Romania is subject to restrictions on acquisition and use change under Law No. 17/2014 on certain measures regulating the sale and purchase of agricultural land situated outside built-up areas. Any title transfer or long-term lease used to secure the project site should have been registered with the ANCPI land registry to be effective against third parties.

If either the grid-connection application or the land rights process was handled defectively by the local partner – wrong forms, missed deadlines with the administrative authorities, failure to pay required fees, or failure to submit required environmental documentation – this may constitute evidence supporting a finding of breach of the JVA milestone obligation, depending on how that obligation was drafted.

Spain-Specific Investor Protection Context

For the Spanish investor, relevant considerations include the structuring of the original equity contribution: whether it was made directly into the Romanian JV entity, through a Spanish holding vehicle, or through an intermediate holding structure in another jurisdiction. The structure affects both the tax treatment of any recovery or loss and the procedural options available in a dispute. Spanish corporate law (Ley de Sociedades de Capital, Royal Legislative Decree 1/2010) governs the Spanish entity's capacity to enter into and enforce the JVA, including any authority limitations on the signatories.

If the investment was structured so that it benefits from the protection of a bilateral investment treaty (BIT) between Spain and Romania – Spain and Romania both became EU member states, and the CJEU's judgment in Achmea (Case C-284/16, 6 March 2018) has significantly affected the enforceability of intra-EU BIT arbitration clauses – this dimension must be carefully assessed. The energy sector has its own investment protection framework under the Energy Charter Treaty, but the application of that treaty to intra-EU disputes has also been the subject of significant CJEU jurisprudence, most recently addressed in Republic of Moldova v. Komstroy LLC (Case C-741/19, 2 September 2021). These issues are complex and highly fact-specific; they should be assessed by reference to the actual dispute resolution clause and the governing law of the JVA, with input from qualified international arbitration counsel.

If you would like to discuss how these international law dimensions might apply to your specific situation, please visit our contacts page or write to info@ferrazwhitmore.com.

Sources

Disclaimer: This article describes a model client situation for informational purposes only and does not constitute legal advice, nor does it reflect an actual Ferraz & Whitmore engagement or outcome. Legal routes are described as options, not guarantees. Applicable law, procedure and the right to provide a given service in each jurisdiction must be confirmed for any specific matter. Ferraz & Whitmore is an independent legal advisory firm based in Lisbon, Portugal; where local representation is required, it works with licensed local counsel. For advice on your situation, contact info@ferrazwhitmore.com.