When one member of a construction or EPC consortium refuses to cooperate on renewing a performance guarantee, the consequences can cascade within days: the project owner may call the guarantee, the consortium faces a contractual default, and the deadlock itself may constitute a breach of the joint venture agreement. The legal challenge is that the same instrument binding the parties together also constrains how aggressively any one of them can act unilaterally. This article sets out the framework for analysing the deadlock, the realistic options for resolving or working around it, and the evidence that must be assembled before any formal step is taken.
Recognising the Situation
The scenario is specific but not unusual in cross-border EPC and infrastructure projects. A consortium of two or more parties has contracted with a project owner – here, let us say a UAE-based employer under a contract governed by UAE or FIDIC terms – and has provided a performance guarantee issued by a bank, typically in favour of the employer. Performance guarantees in international construction projects are frequently structured as on-demand (sometimes called "unconditional") instruments, meaning the employer may call them without proving breach and without the consortium's consent.
The guarantee has an expiry date. The project is not yet complete, so the employer requires the guarantee to be extended. Under the consortium agreement and the underlying project contract, one of the consortium members – let us call it Party B – is responsible for delivering the renewal documentation to the issuing bank within a defined notice window, here 14 days. Party B refuses to do so unless the consortium first amends the participation shares in the joint venture.
This is a classic hostage situation: Party B is using an administrative obligation as leverage to reopen a commercial negotiation that the other party (Party A) considers closed. The employer, meanwhile, is indifferent to the internal dispute and is entitled to call the guarantee if it expires without renewal.
What Is Really at Stake
The immediate commercial exposure is straightforward: a performance guarantee of €3 million, if called by the employer, represents a direct cash outflow. If the guarantee is joint and several, both consortium members are potentially liable to the issuing bank for the full amount of any demand satisfied. If the guarantee is several in proportion to participation shares, the exposure is allocated differently – but the bank's rights against each party and the indemnities between them are distinct questions that must be read from the actual documents.
Beyond the cash exposure, the downstream consequences include:
- Contractual default: Most EPC and construction contracts (including FIDIC 1999 and 2017 suite conditions) treat failure to maintain a valid performance security as a ground for termination by the employer, regardless of project progress.
- Reputational damage: A called guarantee appears on the consortium members' commercial records and can affect future tender eligibility, particularly in public procurement in the EU and GCC.
- Acceleration of the internal dispute: The refusal itself may constitute a breach of the consortium agreement's good-faith and cooperation obligations, which in many civil law systems (including Portuguese law under the Código Civil) are implied terms that cannot be excluded.
- Bank relationship risk: Banks that issue performance guarantees monitor the underlying contract. A called guarantee – or even a contested renewal – can affect the issuing bank's willingness to extend further facilities.
The urgency of the 14-day window means that the analysis and the response must run in parallel, not sequentially.
The Legal Fork: Reading the Documents Before Choosing a Path
No strategic decision can be made without reading four categories of document carefully. What they say – and what they do not say – determines which routes are available.
1. The Consortium or Joint Venture Agreement
The consortium agreement is the primary source of obligations between Party A and Party B. Key provisions to identify immediately include:
- Guarantee allocation: Does the agreement specify which party is responsible for providing, maintaining and renewing the performance guarantee? Is that obligation expressed as a condition precedent to the other party's duties, or is it an independent obligation?
- Decision-making: Does renewal of the performance guarantee require unanimous consent of all parties, or is it within the authority of the lead member or project manager to execute alone?
- Dispute resolution clause: Where, under what rules, and within what timetable must disputes be resolved? This determines whether emergency arbitration is structurally available and, if so, under which institutional rules.
- Change of participation shares: Is there any mechanism allowing a party to condition an administrative obligation on the renegotiation of financial terms? In most well-drafted consortium agreements, the answer is no – the two matters are expressly separated.
- Default and termination provisions: What happens if one consortium member materially breaches the consortium agreement? Can the non-defaulting party exclude or buy out the defaulting member?
2. The Performance Guarantee Instrument
The guarantee document itself will specify the expiry mechanism, the renewal procedure, the demand conditions, and the identity of the applicant (the consortium member or members who provided the counter-indemnity to the bank). Critical questions:
- Is the guarantee on-demand (unconditional) or conditional on proof of breach? Under UAE law and international banking practice, project performance guarantees are generally on-demand instruments, following the model of the Uniform Rules for Demand Guarantees (ICC Publication No. 758, URDG 2010), which is frequently incorporated by reference.
- What is the precise mechanism for extension? Some guarantees require the bank to issue an amendment; others have an automatic extension clause triggered by the employer's non-release. The bank's internal process for amendments will typically require application from the account party – usually the consortium – which is where Party B's cooperation becomes critical.
- Does the guarantee permit a unilateral extension application by any one consortium member? If the consortium is jointly and severally liable as applicant, some banks will accept an extension instruction from either party; others will not act without both signatures.
3. The Project Contract (EPC or Otherwise)
The project contract defines the employer's rights in relation to the performance security. Under the FIDIC 1999 EPC/Turnkey (Silver Book) and the 2017 EPC suite, the employer has a right to call the security on the occurrence of defined events, including expiry without replacement. The employer's notice obligations and any cure periods before a call must be identified – this may create a short additional window for action.
4. Bank Correspondence and Notices
Assembling all written communications from the issuing bank (expiry notices, reminder letters, amendment request templates) and from the employer (any notice of non-renewal or intention to call) is essential. These documents establish the factual timeline and may show whether any notice periods are still running.
Realistic Routes and Their Trade-offs
Route A: Direct Bank Engagement (Bridge Security / Unilateral Application)
If Party A is itself a named applicant under the guarantee, or if the consortium agreement gives the lead member authority to deal with the bank, it may be possible to approach the issuing bank directly for an extension without Party B's signature. This is the fastest route if it is structurally available. The bank will assess its own credit risk and the terms of the counter-indemnity before agreeing. Party A may need to provide additional cash collateral or a counter-indemnity from its own balance sheet to cover the bank's exposure.
Advantages: Preserves the guarantee without litigation; avoids employer call; buys time for the underlying JV dispute to be resolved separately.
Disadvantages: May not be possible if the bank requires both signatories; Party A takes on additional credit exposure; does not resolve the underlying dispute with Party B.
Route B: Negotiated Bridge with Reservation of Rights
Party A can propose to Party B a short-term bridge arrangement: Party A provides the counter-indemnity necessary for the bank to extend the guarantee on a without-prejudice basis, explicitly reserving all rights arising from Party B's refusal to cooperate. This separates the immediate commercial crisis (the guarantee expiry) from the medium-term legal dispute (Party B's breach and any renegotiation claims).
Advantages: Pragmatic; demonstrates good faith; avoids employer call; creates a documented record of the breach.
Disadvantages: Requires Party B to agree to the reservation-of-rights framing (or for Party A to act unilaterally under a right it has verified it possesses); may be read by Party B as capitulation if not drafted precisely.
Route C: Emergency Arbitration / Interim Relief
Many institutional arbitration rules now provide for emergency arbitration or expedited procedures. If the consortium agreement contains an arbitration clause, it may be possible to seek emergency interim measures – most commonly an order requiring Party B to cooperate with the guarantee renewal on pain of cost sanctions or damages.
The major institutional rules providing for emergency arbitration as of 2025 include:
| Institution | Mechanism | Approximate Timetable to Emergency Order |
|---|---|---|
| ICC (Rules 2021, Art. 29 and Appendix V) | Emergency Arbitrator | Order within 15 days of EA appointment |
| LCIA (Rules 2020, Art. 9B) | Expedited Formation / Emergency Arbitrator | Application responded to within 3 days |
| SCC (Rules 2023, Appendix II) | Emergency Arbitrator | Decision within 5 days of appointment |
| DIAC (Dubai, Rules 2022, Art. 13) | Emergency Arbitrator | Order within 15 days of appointment |
| ADCCAC (Abu Dhabi, Rules 2013/amended) | Expedited procedure | Dependent on tribunal formation |
Even the fastest emergency arbitration timetable – five to fifteen days for an order after appointment – may be longer than the contractual window. Moreover, an emergency arbitrator's order is not self-executing: it cannot compel the bank to extend the guarantee. The order would bind Party B to cooperate; enforcing non-compliance then requires further steps. Courts in some GCC jurisdictions have varied approaches to the enforceability of emergency arbitration orders, and local licensed counsel must be consulted on the enforcement position in the UAE specifically.
Advantages: Creates a formal legal record; may have deterrent effect on Party B; preserves rights under the consortium agreement.
Disadvantages: Timeline risk in the context of a 14-day window; enforcement uncertainty in some jurisdictions; cost and management distraction; risk of irreparably damaging the working relationship within the consortium.
Route D: Preservation of Rights and Damages Claim
If the guarantee is called because Party B refuses to cooperate and no bridge arrangement can be concluded in time, Party A's focus shifts to a damages claim against Party B for the loss caused by the breach of the consortium agreement. The strength of this claim depends on the clarity of the obligation, the documented refusal, and the causal link between the refusal and the call. This is not a preferred outcome – it is the fallback once the immediate crisis has passed.
Typical Mistakes and What Cannot Be Promised
In this type of situation, several errors recur across cases and jurisdictions.
Treating the bank as a neutral administrator
The issuing bank has its own legal position. It is not obliged to extend the guarantee simply because one consortium member requests it; it will assess its own credit exposure, the terms of its counter-indemnity from each party, and any internal compliance requirements. Early, direct and documented communication with the bank – setting out the consortium's position and requesting the bank's confirmation of the extension process – is essential. Banks do not generally take sides in JV disputes, but they respond to clear, documented instructions from authorised parties.
Assuming the guarantee call can be stopped by injunction
Performance guarantees that are structured as on-demand instruments are almost never restrained by injunction in common law systems (the established principle from Edward Owen Engineering Ltd v Barclays Bank International Ltd [1978] QB 159 in English law) unless there is clear evidence of fraud. UAE courts and DIFC courts take a similarly cautious approach to restraining demand guarantees. Parties who assume that a court will intervene before the employer makes a demand are usually mistaken.
Conflating the consortium dispute with the bank relationship
The obligation to renew the guarantee runs between the consortium and the bank. The dispute about participation shares runs between Party A and Party B. Mixing these in correspondence – for example, writing to the bank explaining the internal JV dispute – can create confusion and may inadvertently provide the employer or the bank with information that affects their own decisions.
Assuming emergency arbitration solves the problem
As noted above, an emergency arbitrator can order Party B to cooperate. It cannot compel the bank to extend the guarantee; it cannot stop the employer from making a demand; and enforcing the order against an uncooperative party in a cross-border setting takes time and resource. Emergency arbitration is a tool, not a solution.
Failing to document the refusal
Every step of Party B's refusal – the initial request, the response, any conditions imposed, the written notice of refusal – must be documented in writing as it happens. If the matter proceeds to arbitration or litigation, the contemporaneous record is the most important evidence of breach and of Party A's good-faith attempts to resolve the deadlock.
Documents and Evidence: What to Assemble Now
The following checklist is not exhaustive but represents the minimum documentation needed to advise on options and to begin any formal process.
- Consortium / joint venture agreement (all versions, including any amendments and side letters)
- Performance guarantee instrument (original text, any amendments, expiry notice from the bank)
- Bank correspondence (renewal request templates, reminders, the bank's stated position on the extension process)
- Project contract (relevant provisions on performance security, employer's rights on expiry, notice requirements)
- Employer notices (any communication from the project owner regarding the guarantee status or intention to call)
- Internal communications between consortium members regarding the renewal (emails, meeting minutes, formal notices)
- Corporate authorisations (who has authority to sign renewal instructions on behalf of each consortium member; board resolutions, powers of attorney)
- Financial statements or bank facility letters showing each party's capacity to provide counter-indemnity or cash collateral
- Any prior correspondence about participation share changes (to establish whether this was an agreed renegotiation or a unilateral demand)
If the consortium agreement or the guarantee document is in Arabic, a certified legal translation will be needed before any formal step can be taken. This should be commissioned immediately, in parallel with the document review, to avoid losing time.
Timeline and Cost Drivers
The 14-day window is not simply a countdown to the guarantee expiry. It is a sequence of sub-deadlines that must be mapped against each route.
- Day 1–2: Document assembly; initial legal review; bank contact to confirm extension process and any bank-side deadlines for receiving amendment instructions.
- Day 2–4: Written notice to Party B documenting the refusal and stating the consequences; simultaneous assessment of whether Party A can apply for the extension unilaterally.
- Day 3–5: Decision on bridge arrangement; if emergency arbitration is to be filed, the application must be prepared and submitted so that the institution can appoint an emergency arbitrator within the window.
- Day 5–10: Bank amendment process (if proceeding); emergency arbitrator appointed (if proceeding under ICC or DIAC rules); employer to be notified of steps being taken.
- Day 10–14: Confirmation of extension; or, if the extension fails, preparation of damages claim documentation and notification to the employer of the internal dispute.
The principal cost drivers in this type of situation are: (a) the cost of providing additional collateral to the bank if Party A must bridge alone; (b) emergency arbitration filing fees and counsel costs – ICC emergency arbitrator fees and costs are set out in the 2021 Rules and are not trivial; (c) translation costs; and (d) local counsel fees in the UAE, which will be essential for bank negotiations and any enforcement steps.
The cost of acting is almost always lower than the cost of a called guarantee plus a contested damages claim. That said, no adviser can guarantee any particular outcome, and the choice of route will depend on the specific documents and the specific bank's position – neither of which can be assessed without reviewing the actual file.
Decision Checklist
- Read the consortium agreement: Confirm in writing which party is obliged to provide the renewal package and whether that obligation is unconditional.
- Read the guarantee: Confirm whether it is on-demand, who the named applicant is, and what the bank requires to process an extension.
- Contact the bank: Do this in writing, today. Ask for the bank's extension process, the last date it can accept instructions, and whether a unilateral instruction from Party A is structurally possible.
- Issue written notice to Party B: Record the refusal formally; state the deadline; reserve all rights.
- Assess the bridge option: Can Party A provide counter-indemnity or cash collateral sufficient for the bank to extend? At what cost?
- Assess the emergency arbitration option: Is the dispute resolution clause institutional and does it provide for emergency arbitrators? Is the timeline realistic?
- Instruct local UAE counsel: Any bank negotiations in the UAE, any enforcement steps, and any interaction with the project owner require a licensed UAE lawyer.
- Instruct Portuguese counsel (if applicable): If the consortium is registered or incorporated in Portugal, or if Party B's assets are in Portugal, local corporate and enforcement advice will be needed.
- Preserve the documentary record: Every communication from this point forward should be in writing and preserved for potential arbitration.
If you are facing a similar situation and would like to discuss how to structure the analysis across the Portuguese and UAE dimensions, you can reach the team at info@ferrazwhitmore.com or visit our contacts page.
The Portugal–UAE Dimension
Cross-border consortia involving Portuguese and Emirati entities introduce several additional layers that affect each of the routes described above.
Applicable law and choice of law
Portuguese law governs obligations between Portuguese entities under the Código Civil (Decree-Law No. 47344 of 25 November 1966, as amended) and the Código das Sociedades Comerciais (Decree-Law No. 262/86 of 2 September 1986). Article 762 of the Código Civil imposes a general obligation of good faith in the performance of contracts, which extends to cooperation obligations in multi-party arrangements. If the consortium agreement is governed by Portuguese law, Party B's refusal to cooperate on the guarantee renewal may constitute a breach of this obligation independently of any express contractual provision.
UAE law imposes equivalent obligations. Articles 246 and 247 of Federal Law No. 5 of 1985 (the UAE Civil Code, as amended) require that contracts be performed in accordance with their terms and in a manner consistent with good faith, and that where mutual obligations exist, neither party may refuse to perform its obligation if the other party offers to perform its own.
If the consortium agreement does not specify a governing law, the conflict-of-laws analysis under EU Regulation (EC) No. 593/2008 (Rome I), applicable in Portugal, will typically identify the law of the country with the closest connection to the contract. In an EPC consortium for a UAE project, that may be UAE law – but the analysis depends on the facts.
Recognition and enforcement of arbitral awards
Both Portugal and the UAE are contracting states to the Convention on the Recognition and Enforcement of Foreign Arbitral Awards (New York Convention, 1958). Portugal has been a contracting state since 1994. The UAE acceded in 2006. This means that an arbitral award obtained in a New York Convention seat can in principle be recognised and enforced against Party B's assets in Portugal (or vice versa), subject to the limited grounds for refusal set out in Article V of the Convention. The enforcement process in Portugal is governed by the Lei da Arbitragem Voluntária (Law No. 63/2011 of 14 December 2011).
Corporate authorisations in both jurisdictions
If the consortium is a contractual joint venture (rather than a separate legal entity), each party will act through its own corporate structure. Confirming the authority of signatories – under Portuguese company law for the Portuguese party and under the relevant UAE free zone or mainland company regulations for the Emirati party – is a prerequisite to any formal step, including an application to the bank.
For further information on the cross-border structuring of this type of analysis, the team at Ferraz & Whitmore works alongside licensed local advisers in relevant jurisdictions. Contact us at info@ferrazwhitmore.com or through the contacts page.
What This Article Is Not
This article describes general legal mechanisms and frameworks relevant to a model situation. It is not legal advice in relation to any specific transaction, dispute or party. The assessment of which route is appropriate in any real case depends entirely on the actual documents, the specific facts, and the jurisdiction-specific advice of licensed local counsel. No outcome is guaranteed by selecting any of the routes described. An independent legal adviser can help map the options; it cannot replace the bank's decision on extension or the arbitral tribunal's assessment of the merits.
If you recognise your situation in this scenario and would like to discuss the document checklist or the cross-border framework, the team is available at info@ferrazwhitmore.com or via the contacts page.
Sources
- Regulation (EC) No. 593/2008 (Rome I) – EUR-Lex – applicable law for contractual obligations in EU/Portugal, retrieved 2026
- Código Civil Português (Decree-Law No. 47344/1966, consolidated) – DRE – good-faith obligations in contract performance (Art. 762), retrieved 2026
- Código das Sociedades Comerciais (Decree-Law No. 262/86) – DRE – Portuguese company law, corporate authorisations, retrieved 2026
- Lei da Arbitragem Voluntária (Law No. 63/2011) – DRE – recognition and enforcement of foreign arbitral awards in Portugal, retrieved 2026
- New York Convention on the Recognition and Enforcement of Foreign Arbitral Awards (1958) – UNCITRAL – enforcement framework for arbitral awards in Portugal and UAE, retrieved 2026
- New York Convention Status Table – UNCITRAL – confirming Portugal (1994) and UAE (2006) as contracting states, retrieved 2026
- ICC Arbitration Rules 2021 (Art. 29 and Appendix V) – ICC – emergency arbitrator procedure and timetable, retrieved 2026
- LCIA Arbitration Rules 2020 (Art. 9B) – LCIA – emergency arbitration procedure, retrieved 2026
- SCC Arbitration Rules 2023 (Appendix II) – SCC Institute – emergency arbitrator procedure and 5-day timetable, retrieved 2026
- DIAC Arbitration Rules 2022 (Art. 13) – Dubai International Arbitration Centre – emergency arbitrator procedure in UAE, retrieved 2026
- ICC Uniform Rules for Demand Guarantees (URDG 758, 2010) – ICC – on-demand guarantee structure and operation, retrieved 2026
- UAE Civil Code (Federal Law No. 5 of 1985, as amended) – UAE Ministry of Justice – good-faith and reciprocal performance obligations (Arts. 246–247), retrieved 2026
- FIDIC Silver Book (EPC/Turnkey, 2017 edition) – FIDIC – employer rights on performance security expiry (Sub-Clause 4.2), retrieved 2026
Disclaimer: This article describes a model client situation for informational purposes only and does not constitute legal advice, nor does it reflect an actual Ferraz & Whitmore engagement or outcome. Legal routes are described as options, not guarantees. Applicable law, procedure and the right to provide a given service in each jurisdiction must be confirmed for any specific matter. Ferraz & Whitmore is an independent legal advisory firm based in Lisbon, Portugal; where local representation is required, it works with licensed local counsel. For advice on your situation, contact info@ferrazwhitmore.com.